The copper ore mill had a single shutdown window to change every shell and head liner, so the whole set had to arrive complete and in order.
We cast the liners in Ni-hard to the mine’s pattern set and hardness specification, heat treated them and numbered every piece. The set was packed in fitting order so the crew could reline without sorting.
02What we did
Cast, hardened, numbered, packed
Cast every shell and head liner in Ni-hard from the mine's patterns
Heat treated to the specified hardness and checked on each liner
Numbered every liner to the relining plan
Packed the set in fitting order for a single shutdown
8wksFrom order to delivery
1stopTo reline the whole mill
100%Of liners delivered in fitting order
“The crates came off the truck in the order we needed them. The reline finished a shift early.”