Container ship at sea

CSCase study · Forging

Rudder stock and stern tube for a feeder vessel

Client[Client name] shipyard
LocationGdańsk, PL
CategoryForging
Duration11 weeks
CompletedAugust 2024

01The brief

A rudder stock and stern tube under class survey

A container feeder vessel needed a new rudder stock and stern tube, made and tested under class society survey to meet the yard's docking slot.

We forged the rudder stock from our own ingot, heat treated and machined both parts and tested them with the surveyor on site. Material certificates, UT reports and the surveyor’s release travelled with the parts.

02What we did

Made and tested under survey

  • Forged the rudder stock from an ingot poured in-house
  • Quenched and tempered, then machined to the class-approved drawing
  • Ultrasonically tested with the class surveyor witnessing
  • Shipped with material certificates, UT reports and the surveyor's release
11wksFrom order to the docking slot
2partsRudder stock and stern tube
0NCRsRaised by the surveyor
“The surveyor's release was in the crate with the parts. The yard fitted them in the planned docking.”
PKP. KowalskiSuperintendent, shipyard